A-1
General
The College of Science maintains a Hurricane Emergency Plan and Continuity of Operations Plan covering all of its departments and facilities
Alert Procedure
Notification Procedure
Activation
Upon receipt of emergency message the Dean activates COOP
Deployment
Assigned personnel respond & report to Dean's conference room as required. If inaccessible assigned personnel will report to the University's Emergency Response Location located at
A-2
Mission Essential Functions
Incident Response Team
A-3
COOP Author & Point of Contact
Dominique Blanchard, Business Manager, 7-3302, dblancha@fau.edu
Planning Assumptions
These plans are limited to emergencies that directly affect College of Science buildings, faculty, staff and students
Purpose
To prepare and guide the faculty & staff of the COS to effectively respond to an emergency that effects the COS
Objectives
To provide a plan for preparing and responding to any emergency effecting the COS
Applicability & Scope
The COS SOP is applicable to all essential functions of the COS, during an emergency as declared by the University that directly effects COS faculty, staff, equipment and the buildings they occupy.
A-4
Mission Essential Functions
Direction & Control
The Dean's office will be responsible for directing the COS response team, based on University instruction to implement the COOP
Alert & Notification
The Dean's office will notify the response team and the Department & Center Chairs for implementing the employee contact phone tree
A-5
Alternate Operations
The Incident Response Team (IRT) will operate out of the College's Dean's Conference room, in the event that this location is unavailable, the IRT will operate out of the Campus Operations Building #69. If the Boca locations are inaccessible the site support location in Davie will be utilized.
Reconstitution
Following the emergency event, each facility coordinator will report to the Dean a damage assessment including, the status of their facility, equipment and research operation requirements. The report should include requirements for reconstitution of the facility and equipment.
A-6
Implementation
Minor Event
A minor event is a non-life threatening emergency that affects COS personnel, equipment or property, such as a minor HAZMAT spill, electrical outage or accident. In this event, the facility coordinator will determine what elements of the COS COOP should be activated
Campus Event
A campus event affects more than one facility on campus and requires a university response. The COS Dean's office will respond appropriately to the university's request to implement any appropriate elements of the COS COOP
Regional Event
A regional event is a major event that affects the county as well as FAU and EHS, such as a hurricane or flood.
A-7
SOP's
Response Plan and SOP's
A-8
Notification
The COOP Point of Contact will notify EH&S of any relocation contact information required to fulfill the implementation of the plan
A-9
Site Support
The COS administration alternate site is located in the Education and Science Building on the Davie campus Room 225
A-10
Building Evacuation
All COS buildings will follow the normal fire alarm evacuation procedures.
Each department in the COS is responsible for the back up and off site storage of their critical records, not stored on the college's central server. The COS central server is backed up and tapes are stored at an alternate location on campus in addition to an off campus site.
Door cards used to identify critical equipment that may require special procedures for its protection (e.g. emergency power to freezers/refrigerators, protection from water damage, water reactive chemicals, etc.) must be placed on all spaces housing such equipment
Communication Plan
The telephone tree established by each department, will be implemented upon notification to the dept chair, or designee, by a member of the Incident Response Team.
Special Needs
COS staff will notify the COOP author concerning any special needs or requirements as they arise, to be incorporated into the annual plan update.
The College of Science buildings have back-up generators to supply power in case of electrical power failure, (except bldg 43). These generators must receive preventative maintenance on a regular schedule. All generators must be kept fully fueled with arrangements for a constant supply of diesel fuel and oil for the duration of all power outages.
FY 2006-07 (Priority Order)
FY 2007-08 and beyond: Fund as many improvements as possible from above list.